GDC MD speaks on de-risking geothermal prospects in Kenya

Carlo Cariaga 


30 Jun 2023 


Synopsis   


 Geothermal Development Company (GDC) in Kenya aims to de-risk geothermal projects and achieve financial sustainability. The Menengai project, with a partial risk guarantee, is progressing well, and the first power plant by Sosian Power is expected to be commissioned soon. The construction of the second power plant by Globeleq will be completed by mid-2025. GDC has drilled 17 wells in the Baringo-Silali project and seeks developers for a 55-MW facility. Additional drilling is planned in the Silali and Kipchuk geothermal fields. GDC's goal is to attain financial sustainability by 2028, primarily through a 100-MW power plant in Baringo-Silali. 



 

Paul Ngugi, the CEO of Geothermal Development Company, aims for financial sustainability for GDC while helping de-risk geothermal projects in Kenya. 


In an interview with Business Daily Africa, Paul Ngugi, Managing Director and CEO of the Geothermal Development Company (GDC) sheds some light on the efforts of the state-owned geothermal developer to de-risk the geothermal prospects in Kenya in order to attract investment and further development. 


According to Ngugi, GDC is a unique company because one of its objectives is to facilitate the participation of the private sector in geothermal development in Kenya by de-risking the prospects. This may mean having to take on the upfront costs and risks of drilling the wells, as has been the case for the Menengai geothermal power project. 


The Menengai project is also the first geothermal project that has been granted a partial risk guarantee. In the case of the 35-MW geothermal power plant by Globeleq, the guarantee was granted by the National Treasury of Kenya. This insulates the project from certain country and political risks, but also increases the country’s debt. 


Updates on ongoing projects 


Ngugi provided a few updates on the projects that GDC is currently working on: 


The first power plant in Menengai by Sosian Power is expected for commissioning by mid-August. 


It will take about 23 months for the construction of the second Menengai geothermal power plant by Globeleq. Thus, it is expected to be operation by mid-2025. 


17 wells have been drilled in the Baringo-Silali project, and this will be enough to support a 55-MW power facility. GDC is now searching for developers and are waiting to carry out a feasibility study to determine the sustainable capacity of the field over a period of 25 years. A consultant will soon be engaged for this study. 


There are plans for drilling in the Silali and Kipchuk geothermal fields by the next year. 


Achieving financial sustainability 


One of the primary objectives of Ngugi is for GDC is to become financially sustainable without having to rely on government funding. The two power plants currently in development in Menengai will not be enough to achieve this goal. However, a planned 100-MW power plant in the Baringo-Silali field will provide GDC financial sustainability. 


Ngugi said that this status can be reached by 2028 if all goes according to plan. At that point, GDC can sustain its operational expenses and have enough spare money for investments. 


 

Source:   www.thinkgeoenergy.com 